We’re pleased to share the great progress of the phases currently under construction at our Wyndfield community in Brantford. Our team is excited to announce that Phase 6B2 is 90% complete, and all homes have closed and are now occupied.

50% of the homes in phase 8A1 are complete, and we are happy to report 60% of homes have closed on Bee Cres., Gillespie Dr., Basket St.; on Holder Dr. 90% of the homes have been framed, and remaining homes will be moving to the drywall stage. Additionally, exterior brick had been completed on 75% of the homes, with 80% of the homes having exterior siding complete.

 

Phase 8A2 is progressing well, with 90% of the homes framed. 20% of the homes on Wilmont Rd., Moneith Dr., and Bellhouse Ave. are at the drywall stage. 15% of the homes on Wilmot Road and Monteith Drive have exterior brick complete, and 10% of the homes have closed and are occupied along Monteith Drive.

 

Curbs, sidewalks, and sod on Cahill Drive will commence in spring, while Phase 8A1 and 8A2 will commence in summer 2023.

New homes in Brantford are now selling at Wyndfield. View our available homes and connect with us for more information at homehunt@empirecommunities.com.

 

Now, learn more about the schools near Empire Wyndfield and the best getaways in Ontario.

SUBSCRIBE FOR MORE INSPIRATION

Get new home design and lifestyle stories delivered straight to your inbox and stay in the loop on all things Empire.

Let's Get Started

Nicole and Karla

New Home Specialists

Nicole and Karla

New Home Specialists

Please complete the form and we will be texting you shortly to:
Assist you with how to schedule a tour
Answer your questions
Find a quick move-in home

START HERE

GET DETAILS